Work delayed for majority of Madinah projects

madina

Projects in Madinah are experiencing a major delay with only 121 out of 656 development projects proceeding according to schedule, according to the Ada (performance) online government program that monitors development schemes.

Ada was launched earlier this month as part of Madina Emir Prince Faisal Bin Salman for the development of the holy city.

Local newspaper, Al-Madinah reported that work on 176 projects was delayed while work on four other projects has completely stopped.

Advertisement

According to Ada, 355 projects are at risk of falling behind while contractors blame the shortage of workers.